Learning from Experience

Dr. Alex Laufer

I was confused and didn't know how to react when Jim Carroll, a highly regarded figure in the construction industry, proudly presented me with his "Nine Elements for Project Success," the product of two years arduous labor. These nine elements were presented as a well-accepted model, as if they were based on solid findings, and were meant to serve as guidelines for the successful management of capital projects. To my mind, however, the nine elements were based on weak hypotheses and were clearly deficient.

Jim, President of Flour Daniel/Morrison Knudsen, LLC, was at the time, February 1988, serving on the Construction Industry Institute (CII) Project Organization task force. The CII, a national research organization established in 1983, is located at the University of Texas in Austin. It brings together 90 owners and construction companies with 30 universities in an effort to improve the management of capital projects.

When I was first invited to join this task force, it was just after it had experienced a breakthrough. In one of its most productive meetings, the task force was able to identify the "Nine Elements for Project Success." The task force then appointed a small team of five members, headed by Jim, to produce a handbook for practitioners that would thoroughly explain each of these nine elements. I met this team at its first meeting, where Jim allowed me to peruse the nine elements in their rough form, and asked me to write a chapter on project strategy. I honestly felt, however, that I could not fulfill his request.

I just could not accept the "Nine Elements for Project Success." First, they did not cover very important areas of capital projects. Second, they were stated as the "one-best-way" principles, completely ignoring the rich variety of project contexts stemming from the different environments, organizations, technologies, projects, and people.

There was another issue complicating the matter for me. I was very flattered being invited to join the CII task because I knew that at that time I was the only foreign scholar invited to work for the CII. It offered me access to some of the most progressive organizations in the world, and the ability to collect invaluable data from them. I came to the CII with the understanding that I was expected to conduct research for them. I did not feel that my accumulated theoretical research findings allowed me to prepare a chapter useful for practitioners.

I spent a full three hours talking with Jim. To be more accurate, I should say arguing and debating with him, often quite heatedly. At first he stonewalled me. I could not produce the tiniest dent in his rock-hard opinion. Jim stubbornly maintained that applying these nine elements was the way, and the only way, to achieve project success. After all, it took the task force two years to agree on these elements, and Jim was clearly in no mood to retreat and re-examine them. He wanted to make further progress and bring back to the task force tangible products, that is, finalized chapters of the handbook.

It was close to midnight when I realized that I would never be able to convince Jim of the weakness of the nine elements, and was almost about to give up. As a last resort, I asked him whether he would be ready to put the nine elements to a personal test. That is, I asked him to see whether the application of the nine elements could explain the success or failure of the projects with which he was involved during his career. Jim confidently agreed to put the elements to the test.

The next day, the entire five-member team received a fax from Jim in which he shared a simple analysis of the seven projects with which he was involved during his career. He rated the projects according to their success -- four projects were rated successes and three were rated failures. He also examined whether the nine elements applied to those projects. Now it was Jim's turn to be confused.

There was very little, if any, apparent correlation between project success and the nine elements. For example, some elements were applied to all seven projects, and some almost to none. Two factors exhibited a most bizarre behavior. They applied to all the failed projects, but they did not apply to all the successful ones.

Jim is an unusually courageous man. He was willing to reflect on his experience and to learn from it, or more accurately in our case, to unlearn from it, and to share his unlearning with us. He was willing to admit that the nine elements could not provide the complete answer. I was very satisfied, especially in light of the fact that now I felt I was able to conduct a study within the CII organizations before attempting to write my chapter.

Denying Uncertainty

But my problems with the task force were not over yet. A year later, I submitted my research report to the task force. The results, based on an elaborate study in 11 CII member companies, were quite shocking to most members of the task force. Among other things, my findings showed that in most capital projects, uncertainty is not resolved early in the life of the project, for example, at the end of project design. Even more troubling was my finding that in most capital projects, not only are the "means uncertainty" (how to do it) resolved late in the project life, but so are the "end uncertainty" (what to do).

Since most members of the task force could not accept that capital projects suffer from uncertainty, and definitely not from "end uncertainty," they adjusted the presentation of my findings. Instead of portraying project planning as a gradual process of lessening uncertainty, they portrayed it as a gradual process of increasing certainty.

The task force's behavior at the conclusion of my study was very much in line with, and may even explain, their behavior from the outset of the study. The task force members felt comfortable in a certain world, and so they denied uncertainty, even in the face of empirical data from within their own organizations. Most of the members were not really interested in learning, even when they lead a research activity. They did not formulate research questions, only research answers. It could be that the mix of contractors and clients put everyone in a marketing mode. Marketing always starts with an answer; research with a question. They hired "researchers" not to find out or understand reality, but to confirm their own beliefs.

This story demonstrates our ability to learn by reflecting on our own experiences, and our inability to learn by promulgating "answering" over "questioning." Learning starts with a question, a problem to be solved, a dilemma to be resolved, and a challenge to be met. Managers who treat questions as annoyances and regard them as signs of ignorance, and who prefer bold assertions and confident statements because they convey a sense of mastery and control (and certainty), are not learning. Questions force deep thinking and reflection. Questions are an invitation to open a conversation; answers are a prelude to shutting it down. Breakthroughs come from a fresh question, not a ready answer.

You can imagine that even at the end of the study I was not yet ready to write the chapter for the practitioners, (you can as well imagine that the task force did not feel an urge to ask me to do it). It took me an additional six years of research and consulting to feel that I was ready to sit down and compose a book of "guidelines" for practitioners. In today's world with its accelerated pace of change, we can't afford to wait six years for knowledge to be shared. Even a year is often too long. By that time a great deal of knowledge is obsolete and irrelevant.

Professor Alex Laufer, Dean of Civil and Environmental Engineering at Technion-Israel Institute of Technology and former Editor-in-Chief of ASK Magazine has long been a proponent of using to stories to disseminate project management knowledge and has authored or co-authored several books devoted to the subject.


THE PROJECT WAS THREE YEARS LATE: BUT AN INCREDIBLE SUCCESS!

It started like any other project. We had a scope statement, a diverse team, a list of interested contractors, and the enthusiastic support of management. We even had binders with an indexed list of the plans deemed essential for successful projects: communication, change management, risk management, and all the others. And although we had challenging cost and schedule requirements, we knew we had an excellent plan. Nothing could prevent us from delivering this project on time and under budget. At least, that is what we thought!

We had hardly started when trouble struck. The first hint of a problem came in the form of questions about our spending curve. The company was concerned about its overall capital spending and it was looking for opportunities to delay major expenditures into the next fiscal year. We were able to oblige initially. We reassessed our schedule and proudly offered a new plan with the most expensive scope deferred to late in the project. The best news was that we would still meet our original cost and schedule commitments.

Our excitement was short lived. No sooner had we submitted our new plan than we were asked to reduce our early spending even more. In fact, each new plan drew the same request. Eventually, we had to admit we could no longer complete the project on time. That is when the second blow struck. We were informed the project was no longer a top priority. In fact, some members of management were advocating our project be canceled. Morale within the project team plummeted to a new low. Just a few short weeks earlier, our project had been priority #1. Success was guaranteed. Now we were on the verge of being shut down.

Our project was intended to increase production by modifying each of our 21 paper machines at four manufacturing plants located throughout the USA. Generally, we were to install control devices designed to reduce defects and allow us to speed up the machines. Some of the technology was new, even unproven, but our technical experts assured us it would work as intended. “A no brainer” they called it. And so we had developed a comprehensive list of which devices were to be installed on which machines, and how much additional production we could expect from each.

However, our sales volume was not developing as anticipated. And as disappointing monthly sales reports continued to accumulate, management became increasingly reluctant to spend any money on increasing production. Eventually we were ordered to put the project on hold, but to be ready to restart at any moment.

It was time for a new strategy. And since we were no longer under a time constraint we decided to reduce our risk by prototyping each of the technologies included in the original scope. We installed and tested each device on a different paper machine. To our surprise, some did not work as intended. They were not the key to increasing the production rate we expected. Some even had the opposite effect. They produced unintended side effects that caused a decrease in production. But fortunately, not all were failures. Some worked much better than we expected, enabling us to increase the production rate by two or three times the amount we had initially estimated.

The obvious solution at this point was to modify our scope. Clearly, we could achieve the same overall production increase by just installing the devices that worked better than expected and abandoning the others. But an even better strategy began to emerge. As the technical experts analyzed the results of our prototypes, new ideas arose. The experts identified modifications that could work even better than the devices that had proven successful. And so we prototyped these ideas too. And as we now expected, some worked and some did not. And the results prompted even more ideas.

Eventually, the company’s sales began to recover and management started asking for increased production. By this time, we had a menu of proven technologies ready for installation. And we were therefore able to quickly reapply the modifications that provided the best return on investment.

But we now had a proven strategy and we resisted the temptation to deviate. We continued to encourage new ideas, but then insisted on testing them on a single paper machine before declaring them ready for reapplication.

We eventually ran out of money five years after the project was initially authorized, and more than three years after our original completion date. But by this time, we had added three times the production increase we had initially promised. We still had to complete all the paper work to explain why we changed the scope and missed our completion date, of course, but nobody really cared. The real project objective was to increase production at an affordable cost, and we had succeeded beyond our wildest dreams.

Real evidence of success came when the company asked us to submit the paper work to initiate another project. This time, we admitted our scope was a guess and sure to be wrong. But management did not care. They just told us to continue with the same approach, and gave us the amount we requested. It was the easiest project approval I ever experienced.

Clearly, if we had treated this as a traditional project we would have failed. We would have achieved our initial cost and schedule commitments, but produced only a fraction of the production increase we promised. Fortunately, unexpected problems arose and we were forced to develop a strategy much more appropriate for the situation. And we delivered what the company really wanted: additional production at an affordable cost.

Hugh Woodward is the President and Managing Editor of pmforum.org, and an internationally recognized leader of the project management profession. He served two terms as Chair of the Project Management Institute and almost six years as a member of PMI's Board of Directors. His professional experience includes projects and programs in manufacturing, construction and IT, and involving both the public and private sectors. He continues to promote the profession as a frequent conference speaker, having addressed audiences in Argentina, Australia, Canada, China, France, Hungary, Israel, the Netherlands, New Zealand, Russia, Singapore, the United Kingdom, and the United States.

Top of Page

Express your views on any PM World Today matter with a Letter to the Editor.

Letters to the Editor are readers comments and observations on the Editorial, Viewpoint Columns, articles, papers or other notices of PM happenings appearing in the monthly issues of the Project Management World Today.

Send a Letter to the Editor!
Read the Letters to the Editor

Editorial Policy: The PMFORUM® has no connection to any national or international project management organization nor does it reflect the policy of any project management professional or commercial organization. The PMFORUM® maintains an objective and impartial view of project management affairs. In the interests of advancing professional project management the PMFORUM® will publish contending and objective views on issues that reflect collegial differences and perspectives